We are pleased to provide a further update to the Dry Bulk Terminal Project in Mariveles as of End Nov 2015. See earlier post to have a background about the project. 

Our piles have been driven to desired depth and currently constructing tie rods as well as concrete RC work. The dry bulk terminal will be completed in 2016 and operational by then. Panamax size vessels will be able to berth and unload bulk materials serving the cement and commodities markets of Philippines.

 

IMG20151124085040 IMG20151124084208 IMG20151124083628 IMG20151124083529 IMG20151124083315

 

Related Articles

GoListid & GoTagID Commercial Launch

GoListid & GoTagID Commercial Launch

On 11 August 2023, Mlion Corporation proudly launched its innovations – GoListid and GoTagID. The celebratory event was graced by Mr Gan Kim Yong, Minister for Trade & Industry. The launch was also attended by representatives from various government agencies,...

WATERFRONT

Flood protection and waterfront structures for berthing facilities for harbours and port projects.

UNDERGROUND

Substructure Foundation Works for Drilling,
Tunneling and Earth Retaining Structures.

RAILS

Crane Rails and Accessories for Port
and Material Handling purposes.

PROJECT SERVICES

Consultancy for design
and feasibility studies.

Sheet Piles

Hot Rolled Cold Formed
MHZ MMZ
MHU MMU
HAT MLL
FLAT WEB

STRUCTURAL SECTIONS

TIE RODS

UPSET END TIE RODS

Need to Estimate a Solution?